Lorimer Road Project Recap (2014-April 2017) and Forecast

PDF (City of Raleigh internal document, secured through a Public Records request) —

Lorimer Road Pre-Design Notes and Schedule

.  .  .

Lorimer Road (2014-0012) Summary:

CITY COUNCIL RESOLUTION for LORIMER ROAD (DC 2014_0012):

Construct a 27’ back-to-back street section with a 5’ wide sidewalk and 6’ setback on the west side and a 3.5’ shoulder on the east side including curb, gutter, drains, and paving for an approximate distance of 2940 lf (from: Kaplan Drive…to: Garland Drive)…APPROVED SEPTEMBER 1, 2015.

  • Approved by Council on September 1, 2015
  • Assessments shall apply at the rate of $32/lf.
  • Properties abutting the street to be improved shall be connected with water mains, sewer mains, and gas mains (if gas mains available).
  • The petition was passed with 70% resident approval.
  • Note: survey letter sent out called for 6’ sidewalk…Council approved 5’ sidewalk

 

CITY COUNCIL RESOLUTION for WOODLINKS DRIVE (DC 2015_0022):

Construct a sidewalk on the east side to match existing sidewalk (approximate length = 217 lf) on Woodlinks Drive and tie into new sidewalk that will be constructed on Lorimer Road.

  • Approved by Council on November 3, 2015
  • Estimated cost of construction = $21,700
  • Note: existing sidewalk ends in middle of power line easement and has a setback of 4.5’…Jimmy said this was okay because the petition approved by Council says to “match existing”
  • Note: this project will be included in the contract for Lorimer Road project but there will be no distinction between the two projects in the contract…only that there are two separate petitions

Continue reading

“Survey Limits Summary”

Lorimer Road “Kickoff Meeting” Survey Limits Summary
PW#: 2014_0012 (project limits from: Garland Drive…to: Kaplan Drive)

 Garland Drive Intersection:

  • Garland Dr: go 150’ (east and west) past Lorimer Rd
  • Lorimer Rd: go 150’ (north) past Garland Dr

 From: Garland Drive…To: Onslow Road:

  • Go 50’ beyond R/W

 Onslow Road Intersection:

  • Onslow Rd (east leg): go 150’ past Lorimer Rd
  • Onslow Rd (west leg): go to rear property line of parcel 1300

 Bushy Creek:

  • Obtain locations and elevations of headwalls, wingwalls, floor, and ceiling of 15’x6’ box culvert
  • Obtain elevations or height above ground of power and CATV cables measured at culvert center

From: Bushy Creek…To Kaplan Drive:

  • Go to front of houses
    • o Except parcel 1300…go to rear property line
    • o Except parcel 4900 (church)…go to 50’ beyond R/W
  • Merwin Rd: go 150’ from Lorimer Rd and 50’ beyond R/W
  • Athlone Pl: go 150’ from Lorimer Rd and 50’ beyond R/W
  • Woodlinks Dr: go to Fairway Ridge Dr and 50’ beyond R/W
  • Locate 15” storm drain pipes in front yards of parcels 1401, 1321, 1319, 1315 as shown in IMAPS
    • o Top of pipes (horizontal and vertical) elevation is adequate (i.e. don’t need inverts) but make sure they are labeled as “top of pipe” elevations
  • Locate 18” storm drain pipe ends crossing under Lorimer Rd (between parcels 1400 and 1401) with inverts
  • Locate 4” diameter rubber (bronze nut in center) well cap in Lorimer Rd pavement that is 2’ inside pavement (north side) and approximately 40’ west of Merwin Rd

 Kaplan Drive Intersection: (do not need topo here…just new infrastructure)

  • Kaplan Dr: go 50’ (east and west) past Lorimer Rd
  • Lorimer Rd: go 50’ (south) past Kaplan Dr

 General Notes:

  • Do not locate distressed pavement areas as mentioned in meeting
  • Locate all driveway culverts with pipe size, inverts, and material
  • Locate water meters (horizontal and vertical) and sewer cleanouts (horizontal only)

.  .  .  .  .  .

See also Map Summary for Drafting Staff